Savana Resources Barosso Portugal lithium dev plans for 23/24

Member of Europium Groupspot_img
Supported byspot_img

Savana announced that the 2023/24 drilling programme at the Barroso Lithium Project is now underway.

The two phase drilling programme encapsulates all the resource, reserve, hydrogeological (water bores) and geotechnical related drilling required for the Project’s Definite Feasibility Study (‘DFS’)

The first phase of the programme is expected to take approximately 2 months, with 60 holes to be drilled from 49 drill pads, totalling approximately 3,235m

Supported by

Phase 2 of the programme will be further defined following the receipt and analysis of the results of the first phase of work, but is expected to take around 6 months and include c. 10,200m of drilling from approximately 166 holes located on 75 drill pads

Data from the programme will be used to upgrade significant portions of the 21.4Mt of Indicated and Inferred resources, which feature in the Project’s overall existing 28Mt at 1.05% Li2O JORC (2012) Compliant spodumene resource

The upgraded resources will then provide the basis for the Project’s first JORC reserve estimate

Savannah expects to complete the DFS in the second half of 2024 and will provide regular news flow from its DFS-related field programme, including assay results from the drilling, over the coming months.

Savannah’s Chief Executive Officer, Emanuel Proença said: “We are entering a busy and exciting period for Savannah as we progress the Barroso Lithium Project towards development and I was pleased to be with the Project team in the Boticas Municipality as we started our 2023/24 drilling programme. The drilling is a critical part of the work required to allow Savannah to complete the Definitive Feasibility Study on the Project, so the beginning of the programme is a key milestone for the Company.”

“In parallel with our efforts to restart drilling, we have also been progressing with other aspects of the DFS including starting work on the RECAPE phase of the environmental licencing process after the appointment of key contractors over the summer.”

“Away from the work on the ground, we are now reinforcing our engagement with other key local and national stakeholders including the relevant government ministries and agencies. We are also maintaining our efforts on the plan to identify commercial partners for the Project who are willing to assist with the financing of the Project’s construction and bring complementary skills or additional opportunities to a long-term partnership with Savannah.”

Supported byElevatePR Digital

Related News

Rio Tinto Assures on 2500 Pages – There is a Solution for Every Danger

Rio Tinto executed a move announced six months ago – they published drafts of environmental impact studies on how harmful the lithium mine in...

Critical Materials Act: Europe’s strategy for securing green technology supply chains

In May 2024, the EU Critical Raw Materials Act (CRMA) came into force, setting ambitious benchmarks for the domestic production and diversification of strategic...

Critical materials and the path to resilience: Europe’s quest for technological independence

The sustainability and resilience of modern economies hinge critically on the availability and management of key raw materials, such as lithium, cobalt and nickel....

“Protect Jadar and Rađevina”: No dialogue with Rio Tinto, their study is illegal

The association "Protect Jadar and Rađevina" announced today that they oppose opening any dialogue with the company Rio Sava Exploration regarding its environmental impact...
Supported by
Supported by
Supported by
error: Content is protected !!