Ormonde Mining said all elements of the crushing plant at its tungsten project in Barruecopardo in Spain will be in place by the end of September.

It said the process element of the firm’s flagship plant is now 70 per cent complete and will begin commissioning at the start of December.

Projected construction costs also remain within the projected budget of €53.6 million, it added.

Supported by

Michael Donoghue, Ormonde’s chairman and interim managing director, said: “It is very pleasing to have achieved another major project milestone during the quarter, with the on-target commencement of commissioning of the crush and screen plant and the water treatment plant, taking the project into its mine commissioning phase.

“This major advancement accompanied progress on the construction of the process plant, where most of the major equipment has been installed and structural works are well advanced,” he said.

“The commissioning of the process plant is now due to commence in early December, slightly later than originally planned, with first tungsten expected to be produced from early February 2019, to commence a new secure supply to the global markets,” Mr Donoghue said.

Source: irishtimes

Supported byElevatePR Digital

Related News

Important Announcement to Our Readers

After years of dedicated efforts to promote the European mining industry and foster a balanced approach between environmental conservation and the responsible exploitation of...

India set to decide on import restrictions for metallurgical coke

India is set to make a decision soon on whether to implement import restrictions on metallurgical coke, a crucial ingredient in steelmaking. According to...

AMMC targets major production milestones by 2030 with ongoing development projects

Almalyk Mining and Metallurgical Combine (AMMC) has set ambitious production goals for 2030, aiming to achieve annual output of 500,000 tons of copper, 50...

Kazatomprom partners with Jordan uranium mining company on joint uranium exploration and extraction

Kazatomprom, Kazakhstan's national atomic company, has entered into a collaboration with Jordan Uranium Mining Company (JUMCO) to jointly explore and extract uranium in Jordan....
Supported by
Supported by
Supported by
error: Content is protected !!