An updated definitive feasibility study (DFS) for the Vares silver project, in Bosnia & Herzegovina, has seen capital costs decline while the project’s net present value (NPV) and internal rate of return (IRR) have increased.

ASX-listed Adriatic Metals this week reported that an updated capital cost estimate for the Vares silver project had estimated that the project would require a $168-million investment, compared with the $173-million estimated in the 2020 DFS

The updated DFS has also increased the project’s post tax NPV from the $1.04-billion reported in the original DFS to $1.06-billion, while the IRR has increased from 113% to 134%.

Supported by

The pay-back period has declined from 1.2 years to 0.7 years, while the project’s all-in sustaining cost estimates have declined from $9.70/oz to $7.30/oz of silver

“The completion of the 2021 DFS is a major milestone for the company, and clearly demonstrates the exceptional potential of the Vares silver project”, said Adriatic MD and CEO Paul Cronin.

“Project delivery and execution risks have been substantially reduced through the simplification of the process flowsheet and initial capital costs lowered against the backdrop of inflationary construction costs, whilst improving the overall project economics. In the design of this project, environmental and economic sustainability have been at the core of our thinking, shaping the project to ensure that its economic and environmental benefits extend well beyond the current mine life, and provide a perpetual benefit to our local community in Vares and indeed, to the BiH economy”.

Cronin said that the company’s focus would now be on finalising project financing, which is well advanced, and concurrently starting constructio,n while continuing to look for marginal improvements in metallurgical recovery, and capital and operating costs.

“Additionally, we have commenced a study to expand the renewable energy production we have at the Vares processing plant, and [to] augment that capacity to ensure that the Vares silver project reduces its carbon emissions significantly, soon after the commencement of commercial production. As demonstrated in our recent exploration results, we are confident that we can expand the resources and reserves at the Vares project and look forward to working with the Vares community for decades to come, jointly demonstrating the benefits of mining operations in a European context”.

Source: Mining Weekly

Supported byElevatePR Digital

Related News

Lithium from Lopare to be supplied to “Mercedes”

The Swiss joint-stock company ARCORE AG, which has identified significant quantities of lithium carbonate, magnesium, potassium, and boron through exploration in the Lopare municipality,...

A large mine is opening in Bosnia and Herzegovina – it is believed to contain gold

In Vareš, in central Bosnia and Herzegovina, the excavation of a mine that could contain gold is beginning as part of a project that...

Le Monde Diplomatique: EU’s Strategic Interest in Lithium Sourced from BiH – Schmidt’s Role Questioned

The European Union has a significant strategic interest in Bosnia and Herzegovina due to its large deposits of minerals and metals that could support...

Consequences of mining: Bosnia’s forests in peril

The forest surrounding Vares is not just a collection of trees but a vital habitat for wildlife, including bears and wolves. However, activists are...
Supported by
Supported by
Supported by
error: Content is protected !!