Savana Resources Barosso Portugal lithium dev plans for 23/24

Member of Europium Groupspot_img
Supported byspot_img

Savana announced that the 2023/24 drilling programme at the Barroso Lithium Project is now underway.

The two phase drilling programme encapsulates all the resource, reserve, hydrogeological (water bores) and geotechnical related drilling required for the Project’s Definite Feasibility Study (‘DFS’)

The first phase of the programme is expected to take approximately 2 months, with 60 holes to be drilled from 49 drill pads, totalling approximately 3,235m

Supported by

Phase 2 of the programme will be further defined following the receipt and analysis of the results of the first phase of work, but is expected to take around 6 months and include c. 10,200m of drilling from approximately 166 holes located on 75 drill pads

Data from the programme will be used to upgrade significant portions of the 21.4Mt of Indicated and Inferred resources, which feature in the Project’s overall existing 28Mt at 1.05% Li2O JORC (2012) Compliant spodumene resource

The upgraded resources will then provide the basis for the Project’s first JORC reserve estimate

Savannah expects to complete the DFS in the second half of 2024 and will provide regular news flow from its DFS-related field programme, including assay results from the drilling, over the coming months.

Savannah’s Chief Executive Officer, Emanuel Proença said: “We are entering a busy and exciting period for Savannah as we progress the Barroso Lithium Project towards development and I was pleased to be with the Project team in the Boticas Municipality as we started our 2023/24 drilling programme. The drilling is a critical part of the work required to allow Savannah to complete the Definitive Feasibility Study on the Project, so the beginning of the programme is a key milestone for the Company.”

“In parallel with our efforts to restart drilling, we have also been progressing with other aspects of the DFS including starting work on the RECAPE phase of the environmental licencing process after the appointment of key contractors over the summer.”

“Away from the work on the ground, we are now reinforcing our engagement with other key local and national stakeholders including the relevant government ministries and agencies. We are also maintaining our efforts on the plan to identify commercial partners for the Project who are willing to assist with the financing of the Project’s construction and bring complementary skills or additional opportunities to a long-term partnership with Savannah.”

Supported byElevatePR Digital

Related News

ACG Metals completes $290M acquisition of Gediktepe mine in Turkey

ACG Metals has successfully completed a $290 million acquisition of the Gediktepe mine in Turkey's Balıkesir Province. The mine, which is currently producing gold...

Osmond Resources acquires major interest in Spanish critical minerals development

Osmond Resources is set to strengthen its position in the European critical minerals market with the acquisition of a significant interest in the Orion...

Turkey pursues China partnership for rare earths processing to boost EV industry appeal

Turkey is seeking to form a partnership with China to develop and process its newly discovered rare earth elements deposit, potentially enhancing its appeal...

Ukrainian company Velta secures €7.3 million EU grant for advanced titanium processing

Ukrainian company Velta, based in Novomyrhorod (Kirovohrad region), has been awarded a €7.3 million grant from the European Union for a four-year project aimed...
Supported by
Supported by
Supported by
error: Content is protected !!